Saturday, December 1, 2007

Finalizing



The crew finished the second coat of stucco and rewrapped the building just in time for a fine snowstorm. I came back on Saturday and did the floor paint.

Thursday, November 29, 2007

Interior finishing



The foam insulation is going on the walls and the plywood is being installed over with Tapcon screws. By tomorrow the paint should be finished.

Running down to the wire




With a goal to get the construction portion done by Friday, we poured the last two slabs and gave the building a first coat of stucco. Because the weather is so cold we have to drape the building and heat it from the inside so the stucco can cure properly.

Tuesday, November 27, 2007

Final pour




On a cold sunny day, we pumped 22 yards of concrete to complete the roof

Wednesday, November 21, 2007

All the metal is in place



The rebar is all in place and the inspector was kind enough to come and approve it. The concrete pour will be Monday after the concrete company opens back up. On Friday we will finish the forms and get the generator pad formed up.

Tuesday, November 20, 2007

Forming the top



The roof forming is finally enclosed with three scaffold towers inside for support. The tie beam is being fabricated and by tomorrow the top should be ready for inspection.

Tuesday, November 13, 2007

The block walls are rising





The missing conduit got mortered in place and the block walls are rising. Notice the way the frame is secured into the block with wire hooks.

Monday, November 12, 2007

Slabs are poured



Although the pour went into the darkness and we finished by headlights, we were able to come back Saturday morning and finish the tops while they were still green.

Friday, November 9, 2007

Ready to Pour



All the forms are finished and the concrete should be here this afternoon

Wednesday, November 7, 2007

Forming in the desert cold



The plywood forms are taking shape quickly and the first two are placed, leveled and we are starting the steel. It won't be all ready until late tomorrow but by Friday we should be ready to pour concrete.

Excavation passes



The city inspector passed the excavation work with removal of some loose dirt. The labor crew arrived and formwork began.

Saturday, November 3, 2007

Moving the Dirt



After evaluating subcontractors, the excavation crew arrived to start scraping away where the surveyors had marked. Monday the excavation work should be ready for inspection.

Monday, October 29, 2007

Getting the Permit


After a visit in person to the building department, the final fee was calculated, a check promised by Fedex and the permit was approved. After consultation with the developer, potential subs were identified and some contacted. By tomorrow the permit/drawings can be picked up, copies made and bids solicited