The crew finished the second coat of stucco and rewrapped the building just in time for a fine snowstorm. I came back on Saturday and did the floor paint.
With a goal to get the construction portion done by Friday, we poured the last two slabs and gave the building a first coat of stucco. Because the weather is so cold we have to drape the building and heat it from the inside so the stucco can cure properly.
The rebar is all in place and the inspector was kind enough to come and approve it. The concrete pour will be Monday after the concrete company opens back up. On Friday we will finish the forms and get the generator pad formed up.
The roof forming is finally enclosed with three scaffold towers inside for support. The tie beam is being fabricated and by tomorrow the top should be ready for inspection.